Wednesday, June 20, 2012

Lumber Shed Construction at the Yards Begins this Week

5 comments
Construction begins this week on the Lumber Shed, an adaptive reuse component that will become the retail centerpiece of the Yards, a Forest City project. The Shed is set to be completed in the third quarter of 2013, according to a press release.

The Yards, which is one of the largest projects in Southeast D.C., has been named the best new public space by City Paper. Seven restaurants and a Harris Teeter were announced this past year in the boilermaker shops, and recently, the Alatmarea Restaurant Group of New York City announced a new Osteria Morini restaurant to open in The Yards in summer 2013.

The area was formerly the Navy Yard Annex then the Naval Gun Factory. Forest City Washington received the chance to redevelop the 42-acre riverfront property site in 2004, and construction began on several parcels within the yards in 2007.

When finished, the Yards will be a 5.5 million s.f. development, completed during three phases during the next 10 to 20 years.

The Lumber Shed - formerly owning up to its name - is located on the edge of the Yards park overlooking the Anacostia River.  The Shed will be a 30,000 s.f., two-level, retail, glass pavilion, which will temporarily house Forest City’s offices on the second floor and include five restaurants.

The inclusion of Osteria Morini and Forest City’s offices means the building is 60 percent leased.

Washington D.C. real estate development news

Wednesday, December 28, 2011

Today in Pictures - Boilermaker Shops

6 comments
Forest City has begun work in earnest on the boilermaker shops, its first retail pavilion at the Yards in the Capitol Riverfront neighborhood. The building was constructed in 1919 as part of the Navy's largest shipbuilding factory, what would become the world's largest naval ordnance plant.

Forest City has announced the following tenants: Buzz Bakery and a brewery, both operated by the Neighborhood Restaurant Group, Austin Grill Express, Huey's 24/7 Diner, and BRB, all expected to open in late 2012. For more historic pictures, see the chronicler of all things southeast - JDLand.





Washington D.C. real estate development news. Photographs by Rey Lopez.

Monday, December 05, 2011

Capitol Riverfront's Harris Teeter Beginning Work this Week

3 comments

Forest City will begin work this week on Parcel D of its Yards development, including a new apartment building and Harris Teeter. Having secured its last required permit on Friday, according to Ted Skirbunt of the Capitol Riverfront BID, Forest City can now begin its 225-unit apartment with a 50,000-s.f. Harris Teeter, 30,000-s.f. Vida fitness center, and 10,000 s.f. of additional retail space.

Gary McManus, a spokesperson for Forest City, acknowledged that initial work is now beginning, larger scale construction is a month away. "While there may be some site mobilization prior to the holidays, the actual excavation won’t begin to any great degree until January... Excavation is likely to be completed by late April/early May."

With construction underway soon, Harris Teeter could still open in 2013, but according to McManus, Forest City is waiting to confirm a project completion / opening date until next spring, after excavation is done and when more signed retail tenants can be announced.

The design by Shalom Baranes Architects is for two buildings that will be expressed as three, with two residential towers (one above the Harris Teeter running along most of 4th Street, shown above), and one shorter retail building located on the corner with a look separate from the residential portion of the project. The retail building includes 30,000 s.f. ground-floor retail topped by the Vida health club (seen at right).

Washington D.C. real estate development news

Wednesday, October 12, 2011

Forest City to Begin Construction of 225 Apartments, Harris Teeter in Southeast

6 comments
With a building permit to construct the next component of the Yards in hand, Forest City says construction of the Harris Teeter and new apartment building is less than two months away. Permits were issued a month ago, and Forest City's Gary McManus confirms that "[e]xcavation [at Parcel D] will commence within the next 60 days... construction will be underway on that site prior to the end of this year."

Currently, Forest City is focused on phase one (of three) of its 42-acre Yards development in Southeast, D.C. With the first-phase Riverfront Park and Foundry Lofts already completed, and the Boilermaker Shops underway, the developer now turns to construction of Parcel D: a 225-unit apartment with a 50,000-s.f. Harris Teeter, 30,000-s.f. Vida fitness center, and 30,000-s.f. of additional retail space.

Parcel D's site runs along the east side of 4th Street, between Tingey and M Street. The project, under general contractor Skanska, aims for late 2013 completion.

Designed by Shalom Baranes, the site includes two buildings that will appear as having three distinct components: two residential towers (one above the Harris Teeter on 4th Street), and a shorter retail and fitness center building on the southernmost section of the lot (as seen above).

Directly across from Parcel D's retail building is the 2-story Boilermaker Shops (Parcel K) which includes 34,500 s.f. of retail with 12,000 s.f. of office space above, expected to deliver in the fall of 2012.

Rounding out phase one of the development are parcels E and N, both still in the design phase.

Along with Forest City's summer announcement that the Harris Teeter was a done deal at Parcel D, the developer revealed that two concepts - one being an artisan brew pub - will be crafted by the Neighborhood Restaurant Group for the Boilermaker Shops. NRG's concepts will share a roof with Buzz Bakery, Huey's 24/7 Diner, Austin Grill Express, brb (be right burger) and Willie’s Brew & ‘cue by Xavier Cervera, who is also remaking the Hawk 'n' Dove on Capitol Hill, and opening a pizzeria with raw bar in Southeast's Canal Park.

Also nearing completion in Southeast is a one-mile stretch of river-walk trail linking Yards Park and Diamond Teague Park & Piers. According to Ted Skirbunt with the Capitol Riverfront BID, the completion - next month - of this connection will create enhanced public access and enjoyment of the Southeast riverfront.

Washington D.C. real estate development news
 